C/P Planning Process
Can you explain the contract/procurement planning
process?
Make versus buy
The first planning decision could be "make versus buy"
This depends on a number of factors
·
Relative economics
·
In-house capacity currently available
·
The need for control or secrecy
·
Advantages of access to supplier
knowledge and skill
·
An opportunity to maintenance a
robust supplier
·
The relative risks involved and
·
Capital investment versus expense
·
for tax purposes
Multiple contracts - 1
·
The second decision may be one
contract
·
Or several overlapping contracts
·
Benefits of multiple contracts
include
·
Possible saving in time
·
I.e. "fast-tracking"
·
Greater visibility and control
·
Greater flexibility in making changes
·
If the requirements are likely to be
"fluid"
Multiple contracts - 2
Disadvantages of multiple contracts include
·
Increased management and supervision
·
For coordination and oversight
·
Liability to other contractors
·
For failure for any one
·
Or failure to coordinate
·
Diffusion of accountability for
results
Solicitation planning process - 1
·
The activities for solicitation
planning include
·
Conduct market analysis
·
Establish degree of uncertainty in
scope
·
Document time and cost objectives
·
Document assumptions and constraints
·
Document best, i.e. least,
contracting risk
·
The result at this point should be
·
A summary of contract requirements
Solicitation planning process - 2
·
Solicitation planning may be further
expanded by the following activities
·
Prepare and issue a request for
information (RFI)
·
But only if needed
·
Analyze and summarize feed back from
requests for information
·
Resulting in
·
An RFI response summary document
Solicitation planning process - 3
The next steps are to
·
Recommend best contracting strategy
·
Recommend most suitable form of
contract
·
Including most appropriate form of
commercial terms
·
Recommend submission evaluation
criteria for screening and weighting
·
Assemble and recommend list of
"approved" suppliers
·
For the work contemplated in the
contract
Solicitation planning output
The preceding steps should result in
·
A set of procurement recommendations
·
Including contract form
·
Selection criteria and
·
A list of suppliers
·
Submitted to the project's project
director/manager