Contract Formulation - Part B
What are the considerations in preparing and forming a
contract? Especially quality and work control, pace and compensation
Contract Formulation
Continued from Issacon #1412 - Part A
Caveat
Note: We are not lawyers, we cannot provide
legal advice
·
Legal texts should be reviewed by
legal experts
·
Knowledgeable in the law of the
relevant jurisdiction
Control of the work - 1
·
The acquirer's control-of-the-work
variable
·
Is the extent to which the acquirer
wishes to exercise control
·
Over the work to produce the product
·
For example
·
Control over a "time-and-materials"
contract is complete
·
Control over a fixed-price contract
is minimal
·
If the acquirer wishes to avoid any
supplier claims for "interference"
Control of work - 2
·
The supplier's control-of-the-work
variable
·
Is really the converse of the
acquirer's control
·
And is the extent to which the
supplier has control
·
And hence responsibility
·
For the performance of the product
·
For example
·
The supplier's control, and interest
in control, is minimal
·
In the case of a "cost-plus" or "time
and material" form of contract
Quality control
·
The quality control variable
·
Is the extent to which the acquirer
takes responsibility for quality assurance, control and testing
·
For example
·
Quality control rests almost entirely
with the supplier
·
In a fixed price contract
·
Although inspection and testing may
be a condition of interim progress payments
Pace of work
·
The "pace of work" variable
·
Depends on whether the rate of
production is optimized
·
For example
·
If the target delivery date is set
sooner
·
Than an optimal program of work
suggests
·
Then the work must be accelerated
·
By applying additional resources, or
overtime
·
Either may imply additional cost to
perform
·
And possibly additional risk due to
increased complexity in coordination
·
If the work is prolonged
·
Extra costs result from idle capacity
Form of compensation - 1
·
The form of compensation
·
Is not so much a variable
·
As it should be a reflection of the
other variables
·
However, it does have a range of
possibilities
·
Example 1
·
If the scope requirements, or scope
of work, are well defined
·
A fixed price is in the best
interests of the acquirer
·
And the best opportunity for
efficient operation and for profit by the supplier
Form of compensation - 2
·
Example 2
·
If the conditions suited to a fixed
price form of contract are not met
·
A fixed price contract may well end
up being more costly to "retro-fix"
·
Or even end up in failure
·
Example 3
·
The software industry is rife with
failed projects
·
Due to the application of
inappropriate forms of contract
·
Not corresponding to the degree of
scope definition
·
To the detriment of both acquirer and
supplier
Form of compensation - 3
·
Example 4
·
A modified form of fixed price
contract is possible
·
Where provision is made for limited
scope variations
·
By incorporating one or more
unallocated sums
·
For use at the discretion of the
acquirer
·
Such a contract may or may not
include incentives
·
Example 5
·
Time and materials compensation is
most appropriate
·
Where the extent of the requirements
are not yet known
·
Or are highly uncertain
Supplier motivation - 1
·
The supplier's motivation variable
·
Is the extent to which a supplier is
motivated to perform efficiently
·
Example 1
·
Motivation is high in any
"fixed-price" or "lump-sum" contract
·
It offers the opportunity to increase
profit
·
By performing most efficiently
·
Providing that quality is not
compromised
Supplier motivation - 2
Example 2
·
Supplier motivation is probably
highest
·
In the supply of standard
off-the-shelf products
·
Since this provides the safest and
quickest return to the supplier
·
Standard products may or may not meet
the acquirer's needs
·
And may still require some degree of
customizing
·
But this solution is usually less
risky to both parties
·
Compared to an all-custom developed
solution