Model Guideline #13 - Part B
Show me typical
guidelines for -
Project Cost
Estimating: Planning Phases
Particulars - 1
Project Cost Estimating
in the Planning Phases provides the basis for
-
Management decision making
-
I.e. commitment of resources
-
Hence, monitoring & maintaining cost control of the project
Particulars - 2
Note: Cost estimating &
control in the planning phases takes place on two levels
-
The cost of the work during the planning phases
-
I.e. the cost of doing the planning, and
-
The cost of the work as a result of the planning
-
I.e. The work of producing the product in the production
phases
Particulars - 3
The Order of Magnitude
Estimate is really no more than an "educated guess" based on
-
A statement of requirements in "Mission" terms, and
-
An outline solution
Note from the accuracy
ranges suggested that
-
Overrun is three times more likely than underrun
-
Because of what we don't know - rather than what we do!
Particulars - 4
The Definition Class
Estimate is
-
Also known as a Feasibility Estimate, Preliminary Investment
Decision, and so on
And is based on
-
Completion of all of the work known to be necessary
-
Including the work of all four project phases
-
Based on past records and past experience
-
And/or parametric costing
-
Applied to the projects major components and systems
Particulars - 5
In addition, the
Definition Class Estimate must allow for
-
The facility/system/product/service future working environment
-
And any special associated risks
This, and following
estimating, should be
-
Consistently based on the "most likely cost under normal/typical
conditions" of each component of the work, and
-
Anticipated variations from these conditions should be factored into
the "contingency" allowances
Particulars - 6
The Implementation
Class Estimate is
-
Also known as an Engineering Design Estimate, Design Control
Estimate, Cost Plan, and so on
And is based on
-
An update of all the work known to be necessary
-
Functional. engineering or configuration design
-
Prior to detailing work and specifications
-
Partly parametric estimating
-
But preferably on developed unit costing
-
Or other form of more detailed estimating
Particulars - 7
For purposes of the
Project Charter
-
This estimate must be converted
-
To a viable working implementation budget
-
Often known as the Baseline Budget
The reason for this
"conversion" is because the way costs are estimated is not the same way
as they are usually collected
Particulars - 8
To enable project cost
monitoring and control
-
The Baseline Budget must match the way the costs will be
collected
Special vigilance is
required in this conversion process
-
To ensure that the project's scope has not been changed in this
process
Particulars - 9
A cost estimate may, or
may not, include an assessment of appropriate contingency allowance
However,
-
A Baseline Budget must include appropriate contingency
allowances, and
-
A policy on how that contingency will be managed
Estimates at all stages
must include all applicable charges such as
-
Overheads, on-costs, carrying charges on borrowed capital, etc.
Definitions and Responsibility
Definitions to be
included
-
Order of Magnitude Estimate, Definition Class Estimate,
Implementation Class Estimate, Parametric Estimating, Baseline
Budget
Primary responsibility
Responsible to