How to Recognize
Project Risks
How do I know if
my project is at risk and, if so, what can I do about it?
Simple
Indications
Some simple
indications that a project is at risk:
·
The project's sponsor does not recognized
that every project is an exercise in risk
·
No risks have been identified, or no
appropriate contingency plans have been developed
·
The project relies entirely on the
contingency allowances
·
The project's goals, objectives, scope
and deliverables are not clearly defined, nor understood
·
Costs, schedules and performance are not
expressed in ranges
More simple
indicators
·
Future timing of activities and events
are vague
·
Standards for performance are absent or
unrealistic
·
"We expect the best there is for
everything!"
·
The project is very different from the
last one
·
A large number of alternatives are
perceived as possible
·
Some or all technical data is lacking
·
Design lacks production or engineering
input
·
Prototype of a key element is missing
·
There is a higher than usual R&D
component
Still more
indicators
·
Some or all environmental considerations
or permits are not considered or available
·
Bids in response to requests for
quotation vary widely
·
Some key subsystems and/or materials are
sole sourced
·
There is a feeling of uneasiness
·
Someone starts "hedging their bets"!
·
Other similar projects have been delayed
or canceled
What can I do
about such a risky project?
·
Here are some simple rules-of-thumb
·
Don't continue the project, or accept one
of its risks, if:
·
The organization cannot afford to lose
·
The exposure to the outcome is too great
·
The project, or situation, is just not
worth it
·
The odds are not in the project's favor
More simple
rules-of-thumb
Discontinue the
project, or avoid the risk if:
·
It is seen as no more than a "fair bet"
·
The benefits have not been identified
·
There appear to be a large number of
acceptable alternatives
·
The greater the number, the greater the
uncertainty
·
One or more of the project's risks does
not support the project objectives
Still more
rules-of-thumb
Discontinue the
project, or avoid the risk if:
·
The Expected Value from the baseline
assumptions is negative
·
Or becomes negative with small changes in
the assumptions
·
The data is unorganized, without
structure or pattern
·
Get more data, or do research!
·
A contingency plan is not in place should
the results prove to be less than satisfactory
Bottom Line
A viable project
is one in which the probability of gain is higher than the probable
consequences of loss
1004 Project Risk
Key Words:
Project risk management, project risk, risk, uncertainty, opportunity
Area of PM Application: Universal
(See IAC #1001)
Topic Level: Process
(See IAC #1002)
Related Topics:
Reference:
What is project
risk?
Be careful how
you say it!
·
In project work
·
Always refer to project risk
·
Why?
·
Because use of the term "risk" (i.e. on
its own) typically refers to risk as defined in the insurance industry
·
Which commonly refers to something
happening to you that you don't like!
·
Project risk is a special case of risk
·
The risk of the project not being
successful
·
We'll deal with the insurance sort in a
later Issacon
Dual meaning
·
In the literature, risk is often used to
imply simply failing to fall into line with the project plan
·
Either over or under
·
This is really normal project progress
evolution
·
And management's responsibility to track
and control
·
After all, schedules and budgets are only
based on best estimates
·
To be handled by management strategy,
tactics and contingencies
Risk in Progress
Evolution
·
If your project is viewed as unsuccessful
simply because
·
It fell behind schedule
·
Or went over budget
·
Perhaps due to poor estimating
·
Or to lower than planned productivity
·
Such situations are evolutionary - not
events
·
That's not usually part of formal project
risk management
·
That's the project team's management
responsibility
Event Oriented
Project Risk
·
While risk is the possibility of an
undesirable outcome
·
Formal Project Risk Management usually
focuses on "Risk Events"
·
Thus
·
Project Risk is the cumulative effect of
the chances of adverse events which could affect the projectís
objectives
·
Or, the degree of exposure to untoward or
turbulent events and their probable consequences
Appropriate Risk
Event Response
·
Note the use of the word "events"
·
For identifying, analyzing and mitigating
unplanned events
·
Or better still, avoiding them altogether
·
Adopt some degree of formal project risk
management
·
And be ready with an appropriate response
Evolution versus
Events
·
As your project evolves
·
It may well fall behind schedule
·
And run over budget
·
Requiring corrective action
·
If, however, the corrective action fails
and you miss a mandated deadline as a result
·
That is indeed an "event"
·
For which you would be well advised to
have a good risk management plan!