Introduction
Project management is a composite activity with multiple
dimensions. Depending on the type and class of project this
management activity can be very complex, not least because
the typical project environment echoes the ‘fractal’ form of
the common garden snail's shell. That is to say, the same
approach can be applied at every level of the management
hierarchy and only the size and branch of the activity
changes. For example: on a very large project, it may well
be subdivided into ‘sub-projects’ each of which is managed
as a project in its own right.
Strictly speaking, such a “large project” should be referred
to as a program, but the analogy is not limited to large
projects. The pieces of any sized project that are parceled
out to otherwise independent operators can be considered,
from their point of view, as a project which they own and
manage.
Similarly, the principles of project management can be
applied to any level or branch of a project that falls under
a different area of responsibility in the overall project
organization. Under these circumstances, it is not too
difficult to see that the problem of different agendas can
arise and the overall goals of the project can become
obscured as a result.
We should also be clear on what we mean by project
management, not in terms of the traditional definitions but
in terms of the scope of this management activity. For
purposes of this paper, we see a distinction between
technical management and project management. Technical
management is the business of managing the technology of the
project whereas project management is the business of
managing the entire endeavor through its project life cycle
process. While we draw this distinction, in the real world
the two must be fully integrated but the combination varies
between different project management application areas.
In the literature, there is a wealth of information
describing projects in all areas of application, what was
achieved, how it was achieved and how successful were the
results. Similarly, there is a wealth of literature
providing advice on how to do project management – and
presumably do it better. Based on this experiential
material, various attempts have been made to assemble
‘bodies of knowledge’ and thereby articulate the role and
content of project management1,2,3. Such documents have been
used in several countries for the development of individual
certification and competence testing, and/or by enterprises
for establishing corporate standards of practice.
In contrast, there appears to be very little content
establishing basic ‘principles’ and theories to support
them. This absence suggests that the building of a project
management discipline is presently based only on
experiential records and opinion and not on any reasonably
logical or theoretical foundation. Ideally,what is needed is
a generally agreed and testable set of elemental
‘principles’ of project management which provide a universal
reference basis for a set of generally acceptable
‘practices’.
To emphasize that we wish to focus on the founding
principles of project management, we will use the term
‘First Principles’. It may be asked “Do we really need a set
of ‘First Principles of Project Management’”? The problem is
that within a corporate environment, understaffing is
generally considered good business practice. However,
projects require contingency allowances to accommodate the
inevitable uncertainty involved so that the practice of
under-resourcing is a recipe for failure. Hence the need to
promulgate a set of generally agreed fundamentals.
So what should be included as a ‘First Principle’? The key
appears to be whether or not the principle is universally
fundamental to project success. (See additional comments
under Discussion: First Principles Generally.) However, the
meaning of project success, like a number of other key
terms, is debatable. So, in order to lay a foundation for
this discussion, we commence with definitions for the
leading terminology we use in this paper.
Definitions We are well aware of the many and varying
nuances arising from different definition wordings, but it
is
the intent, rather than the detail, that we are concerned
with here. (For more on this topic, please see the Wideman
Comparative Glossary of Common Project Management Terms.)
First Principles
In general usage, there appears to be some ambiguity when it
comes to the use of the words “principles and practices”,
Moreover, in the marketplace, the term ‘principle’ appears
to be used indiscriminately to mean either.
Webster defines a ‘Principle’ as “a general truth, a law on
which others are founded or from which others are derived;
provides a guide to conduct or procedure…
Cleland and Kerzner go further in defining ‘Principle’ as
follows:
1. A fundamental rule or law of action based upon desirable
ends or objectives. A principle is more basic than a policy
or a procedure and generally governs both.
2. A fundamental truth, or what is believed to be truth at a
given time, explaining relationships between two or more
sets of variables, usually an independent variable and a
dependent variable; may be descriptive, explaining what will
happen, or prescriptive (or normative), indicating what a
person should do. In the latter case, principles reflect
some scale of values, such as efficiency, and therefore
imply value judgments.
Webster defines ‘Practice’, on the other hand, as “customary
use, method or art of doing anything…”.
Cleland and Kerzner do not include a definition for this
term.Thus, ‘Practice’ is a way of doing things and
‘Principles’ and ‘Practices’ may be distinguished by the
difference between ‘What’ and ‘How’. In Cleland and
Kerzner’s second definition there appears to be some overlap
perhaps reflecting the confusion evident in the marketplace.
At first glance it would appear that the use of the
qualifier ‘First’ with ‘Principle’ is redundant. However, in
scientific circles, the idea of ‘First Principles’ is a
common concept describing root or axiomatic ideas that
provide the absolutely essential foundations for further
thought and analysis. Since we are interested here in the
very origin of project management, we use the term ‘First
Principle’ advisedly.
Project
There are many and varying definitions of the term
‘project’. For our purposes: “A project is a novel
undertaking to create a new product or service the delivery
of which signals completion. Projects are typically
constrained by limited resources.” Also for our purpose,
such a project is viewed from the perspective of the ‘owner’
or ‘sponsor’ and begins when resources are dedicated to its
specific goal, commencing with activities such as ‘Concept
Exploration’, ‘Initiation’ or ‘Inception’, etc.
Product Scope
Product Scope, typically but loosely just referred to as
’scope’, is used in the narrower sense of “The definition
that describes the project’s product deliverables.”6 This is
not the same as the ‘Scope of Work’ which describes “The
work involved in the design, fabrication and assembly of the
components of a project’s deliverable into a working
product.”7 The term ‘product’ includes the delivery of a
‘service’.
Quality Grade
We use the term ‘Quality Grade’ to distinguish it from the
term ‘Quality’ which is typically taken to mean “The
totality of features and characteristics of a product or
service that bear on its ability to satisfy stated or
implied needs.”8 Quality Grade on the other hand is “A
particular attribute of an item, product or service, which
meets all minimum project requirements but which may be
delivered according to a class ranging from ‘utility’
(purely functional) to ‘world class’ (equal to the best of
the best).”9 As such, Quality Grade is a separate variable.
It is also the most enduring in terms of project success.
Project Success
Project success is a multi-dimensional construct10 that
inevitably means different things to different people. It is
best expressed at the beginning of a project in terms of key
and measurable criteria upon which the relative success or
failure of the project may be judged. For example, those
that11:
· Meet key objectives of the project such as the business
objectives of the sponsoring organization, owner or user,
and
· Elicit satisfaction with the project management process,
i.e. that the deliverable is complete, up to standard, is on
time and within budget, and
· Reflect general acceptance and satisfaction with the
project’s deliverable on the part of the project’s customer
and the majority of the project’s community at some time in
the future.Project success is closely linked to opportunity
and risk. Projects by their nature are risky endeavors and
some project hazards cannot be entirely avoided or mitigated
even when identified. Since project success may be impacted
by risk events, it follows that both opportunity and risk
are necessarily shared amongst the participants.
It is also important to note that success criteria can
change with time. That certain objectives were not achieved
does not necessarily mean that the project was a failure.
Project Customer and Project Community
Rather than project stakeholders and constituents, we prefer
the more focused terms ‘customer’ and ‘community’. Project
Customer is the immediate recipient of the product of the
project, who will use it and is in the best position to
evaluate its acceptability after a suitable period of
learning. The ‘customer’ may be more than one person.
Project Community includes anyone who is impacted by project
activities or its product, either directly or indirectly and
for better or worse.
Criteria for Establishing a First Principle
To identify a set of ‘First Principles of Project
Management’ we must set criteria for their acceptance or
exclusion. The following criteria are proposed.
A First Principle of Project Management must:
1. Express a general or fundamental truth, a basic concept.
2. Make for a high probability of project success as defined
above. The corollary is that the absence of the condition
will render project success on a majority of the key
criteria as being highly improbable.
3. Provide the basis for establishing logical processes and
supporting practices that can be proven through research,
analysis and practical testing.
In addition and ideally, a First Principle should:
1. Be universal to all areas of project management
application.
2. Be capable of straight forward expression in one or two
sentences.
3. Be self-evident to experienced project management
personnel, and
4. Carry a concise label reflecting its content.
First Principles of Project Management
Based on the foregoing criteria, the following ‘First
principles’ are proposed. These principles build extensively
on the work of John Bing12. All the principles presume
certain assumptions about the cultural ambience in which the
project takes place. An ambience that encourages and
sustains teamwork and honesty (See The Cultural Environment
Principle below) and demonstrates that13:
1. Everyone is working towards the same or similar project
goals, whatever those might be
2. Everyone is clear and agrees on who the customer is
3. Appropriate levels of skill or experience are available
as needed, and
4. Everyone wants the project to succeed.
An equitable commitment between the provider of resources
and the project delivery team must exist
before a viable project exists.
The provider of resources (money, and/or goods and services,
and general direction) is typically called the project’s
‘owner’ or ‘sponsor’. The project delivery team is
responsible for developing appropriate strategies, plans and
controls for applying the necessary skills and work to
convert those resources into the required deliverables or
product. An ‘equitable commitment’ means that both parties
are sufficiently knowledgeable of the undertaking, the
processes involved and their associated risks, and both
willingly undertake the challenge.
The owner of the project must understand that even with
appropriate management controls in place, there must be a
sharing of the risks involved. The attributes of both
parties should encompass relevant skills, including those of
the technology involved, experience, dedication, commitment,
tenacity and authority to ensure the project‘s success. (See
also Discussion: Commitment Principle below.)
2. The Success Principle
The measures of project success, in terms of both process
and product, must be defined at the beginning of the project
as a basis for project management decision making and
post-project evaluation.
It is axiomatic that the goal of project management is to be
successful, otherwise the incurring of this management
overhead is a valueless exercise. First and foremost,
project success needs to be defined in terms of the
acceptability of the project’s deliverables, e.g. scope,
quality, relevance to client needs, effectiveness, etc; and
secondly in terms of its internal processes, e.g. time,
cost, efficiency, etc. The timing of the measurement of
success itself may also need specifying. Without agreement
on the project’s success criteria, it will not be possible
to measure its ultimate success.
It goes without saying that these measures of project
success should be verified and reinforced throughout the
project life cycle. As a corollary, if the success measures
are no longer in alignment at any point, it should be
perfectly acceptable to abort the project or at least halt
it pending re-evaluation. (See also Discussion: Success
Principle, below.)
3. The Tetrad Trade-off Principle
The core variables of the project management process,
namely: product scope, quality grade, time-toproduce and
total cost-at-completion must all be mutually consistent and
attainable.
This principle is an extension of both the Commitment
Principle and the Success Principle. The core variables of
product scope, quality grade, time-to-produce and total
cost-at-completion collectively, often loosely referred to
as scope, quality, time and cost, respectively, are measures
of internal project management efficiency. If these
variables prove not to be mutually consistent and
attainable, the commitment is neither equitable nor are key
success criteria likely to be met. The interrelationship of
these four separate variables are somewhat similar to a
four-sided frame with flexible joints. One side can be
secured and another moved, but only by affecting the
remaining two.
A strategy encompassing first planning then doing, in a
focused set of sequential and progressive phases, must be in
place.
The genesis of the project life cycle process, in its most
basic form, is to be found in the very term “project
management” itself. A project has, by definition, a start
and a finish. The essence of management is to ‘plan’ before
‘doing’. Hence the most fundamental project life cycle
process consists of four sequential periods of ‘Start’,
‘Plan’, ‘Do’ and ‘Finish’. Of course these four periods can
be expanded into separate phases each with their own interim
deliverables and Executive Control Points (or Emergency Exit
Ramps.) These can be designed to suit the control
requirements of every type of project in every area of
project management application. Indeed, this sequence is, in
effect, equally applicable at every level and branch of the
project organization. It is also just as relevant where a
‘fast-track’ strategy or an iterative approach is adopted.
The importance of this life cycle process and its influence
on the management of the project cannot be over emphasized.
This relatively short-term life-to-death environment, and
the consequences that flow, is probably the only thing that
uniquely distinguishes projects from non-projects14
5. The Management Principle
Policies and procedures that are effective and efficient
must be in place for the proper conduct and control of the
project commitment.
This principle is an extension of the strategy principle.
The Strategy Principle determines what is going to be done
and when. The Management Principle establishes how it is
going to be done and by whom.
The attributes of this management control encompass the
project’s assumptions, its justification and a reference
baseline in each of the core variables as a basis for
progress measurement, comparison and course adjustment. The
attributes of good policies and procedures encompass clear
roles and responsibilities, delegation of authority, and
processes for maintaining quality, time and cost, etc. as
well as managing changes in the product scope and/or scope
of work.
6. The Single-Point Responsibility Principle
A single channel of communication must exist between the
project sponsor and the project team leader
for all decisions affecting the product scope.
This principle is an extension of the management principle
and is necessary for effective and efficient administration
of the project commitment. For example, the owner of the
eventual product, if represented by more than one person,
must nevertheless speak with one voice through a primary
representative with access to the sponsor’s resources.
Similarly, the project’s delivery team must always have a
primary representative. However, this only applies to the
decisions affecting the product scope and hence the
project’s overall cost and schedule. In all other respects,
free and transparent communication is indispensable for the
coordination of a complex set of project activities.
Therefore,
this principle must not in any way inhibit the proper
exchange of information through the network of project
communication channels that is required to integrate all
aspects of the project.
7. The Cultural Environment Principle
Management must provide an informed and supportive cultural
environment to ensure that the project delivery team are
able to work to the limits of their capacity. The ability of
a project delivery team to produce results both effectively
and efficiently is highly dependent upon the cultural
environment. This ‘cultural environment’15 encompasses both
internal and external project relations and values.
Internally, the management style of the team leader must be
suited
to the type of project and its phase in the project life
cycle. Externally, the management of the organization in
which the project takes place must be supportive and the
environment free of obstacles.
Discussion
First Principles Generally
Issue #1: Do we really need “First Principles of Project
Management”? Most people seem to have managed very well
without them, that is, until the trouble starts. Most
projects take place in a corporate environment but the
approach to corporate management and to project management
are very different. Marie Scotto has provided a compelling
list of differences16. Perhaps the most significant is that
“The business community believes in understaffing which it
can prove is generally good business most of the time.” In
contrast, projects are especially risky by their nature and
need a margin of surplus if for no other reason than to take
care of contingencies. For a project to be under-resourced
is a recipe for failure. Consequently, a set of credible
‘fundamentals’ is sorely needed for making an adequate case
to corporate management for providing the required support.
Issue #2: What should be included as a First Principle and
what excluded? The key criterion is thought to be whether or
not the principle is universally fundamental to project
success as defined. For example, without some form of
commitment there can be no project and hence no possibility
of success. On the other hand, there are many major tools
and techniques the application of which might be considered
as essential to success.
For example, a formal work breakdown structure, schedule
network, earned value analysis, change control process and
so on. However, projects in many application areas are run
successfully without applying these tools. So, while they
may be considered good practice, they are not necessarily
essential. Each such tool undoubtedly relies on its own set
of principles which may be considered as secondary to the
First Principles.
Commitment Principle:
Issue #3: It has been suggested that there should be a
‘Business Principle’ which states that the project must be
in alignment with the sponsoring organization’s goals. This
is a valid comment, but on balance this should be corporate
management’s responsibility to determine that before
embarking on the project. Nevertheless, a prudent project
manager will satisfy him/herself that the project is indeed
so aligned, and justified.
Issue #4: Similar to Issue #3, it has been suggested that
there should be a separate ‘Technical Principle’ which
states that the project leader and team members must be
knowledgeable in the technology of the product. This is
certainly true, but is deemed to be covered by the
Commitment Principle in that an ‘Equitable Commitment’ is
not possible without an understanding of the risks involved
including those associated with the technology.
Issue #5: It must be recognized that every project ‘evolves’
through its life cycle and the commitment and tradeoffs will
similarly evolve. On most projects the players will also
change, as it moves through its life cycle, simply to meet
the changing level of effort and skills required in each
phase. Nevertheless, an ‘equitable commitment’ can and
should exist for every phase of the project if the project
is to remain viable.
Once again, in the real world, many projects are not set up
this way. Resources are short changed or reprioritized and
unattainable deadlines are set, often for the reasons
described by Marie Scotto (see Issue #1 above.) Thus, the
absence of this and the following principle simply means
that the probability of success is greatly diminished – if
not impossible.
Success Principle:
Issue #6: It has been suggested that the issue of success is
so obvious as to be unworthy of a first principle. However,
‘success’ for a project and how it will be measured after
completion does need to be defined at the beginning of the
project. The most important reason is to provide an on-going
basis for management decision making during the course of
the project. Contrary to conventional wisdom, there have
been many projects that have been “On time and within
budget” but the product has not been successful, and
similarly many that have not been “On time and within
budget” yet by other measures the product has been very
successful. Motorola’s Iridium is a good example of the
former while the movie ‘Titanic’ is a good example of the
latter.
We believe that project success is much more than just
“Doing what you set out to do”. It is also about whether
what you are doing is in fact the right thing to do. We
believe that the ultimate goal of a project, and therefore
its measure of ‘success’, should be satisfaction with the
product on the part of the customer. As noted earlier, the
assumption is that the ‘customer’ is clearly identified.
However obvious and sensible the setting of project success
criteria at the beginning of a project may seem,
regretfully, it is not currently a common practice. Without
defining these success criteria, how can agreement be
reached on a particular project’s priorities, trade-offs,
the significance of changes, and the overall effectiveness
and efficiency of project management post-project? For this
reason, a lot of conclusions drawn from experiential
material could also be very questionable.
As Gerald Neal points out, the reality of life on many
projects is that everyone on or associated with it does not
have the same aspirations and goals. As a result “the
project gets pulled in many different directions … [by]
…status, pride, power, greed…” In most cases, this may be a
little exaggerated, but even at the most elementary level,
the project owner will be interested in benefiting from the
product while the workers on the project will be interested
in benefiting from the process. This makes the definition of
a project’s success even more important - to provide a
reference baseline for the correction of divergent progress.
Tetrad Trade-off Principle:
Issue #7: Although the term ‘Tetrad Trade-off’ has been in
the literature for some years17, objection has been raised
because the term is unfamiliar. Perhaps this is the very
value of the term – to emphasize that there are four
separate but interactive variables (scope, quality, time and
cost) rather than just three as in the old view of ‘Triple
Constraint’ (time, cost and performance.) Thus, quality, the
most enduring variable of the four when it comes to project
success, is given new prominence. It should be stressed here
again that quality means ‘Quality Grade’, i.e. the measure
of level or class (utility to world-class) as distinct from
‘Quality Conformance’, i.e. “conformance to specified
requirements”.
Cultural Environment Principle
Issue #8: Once again, the reality is that many managements
place obstacles in the way of project progress, perhaps
unwittingly because of management’s functional heritage. Yet
another reason for a solid set of Project Management First
Principles.